電蒸汽鍋爐廠家http://www.officechairs.com.cn/介紹管道安裝前,應(yīng)檢查管材材質(zhì)。各類管道應(yīng)沿墻敷設(shè),保證安裝操作空間和維修方便。
1、電蒸汽鍋爐給水管道安裝應(yīng)由設(shè)備接管端開始,以設(shè)備上管道接口為基準(zhǔn)向外延伸,并注意在供熱管之下安裝。
Electric steam boiler feed water piping equipment installation should begin to take over the side to the device interface as a benchmark pipeline extends outward, and note installed under the heating pipe.
2、電蒸汽鍋爐熱水管道安裝時,應(yīng)具有一定的坡度,方向與熱水流向相同。最高點(diǎn)設(shè)排汽閥,排水管接至地面排水溝。最低點(diǎn)設(shè)疏水閥,保證操作方便。
When electric steam boilers, hot water pipe installation, you should have a certain slope, with water flowing in the same direction. The highest point of the exhaust valve is provided, drain connected to the ground drains. The lowest point of the trap set up to ensure easy operation.
3、電蒸汽鍋爐排污管道安裝與設(shè)備及閥門采用法蘭連接外,一律采用焊接。管道上應(yīng)盡量少用彎頭。
Electric steam boiler blowdown valve and piping and equipment installation flange connections, all welded. Pipe elbow should be used sparingly.